Thousands of turns in EMMA
I’m delighted to inform you that during the latest EMMA commissioning run earlier this week further significant milestones have been achieved.
Circulating beams with more than a thousand turns have been achieved and commissioning of the RF system is also well advanced.
The next EMMA operating period starts on 30th August when work resumes to demonstrate evidence of acceleration and transverse stability with resonance crossing, which are major goals for this novel particle accelerator.
Neil Bliss
EMMA Project Manager